Spring 2027 Target
The schedule coordinates with the opening of the JW Marriott Detroit Water Square Hotel, with completion planned before the NCAA Final Four.
Station upgrades scheduled from September 2026 through early March 2027.
Water Square is receiving its first major station upgrade since the Joe Louis Arena era. Construction runs from September 2026 through early March 2027. Reinvestment in the station supports public transportation for the neighboring community while improving the appearance and condition of the facility.
The schedule coordinates with the opening of the JW Marriott Detroit Water Square Hotel, with completion planned before the NCAA Final Four.
The Neighborhood Advisory Committee's (NAC) Accessibility, Mobility & Traffic Priorities identified the station's age and condition. The work includes NAC-requested interior beautification and security enhancements.
DTC is working with its contractors to maintain safe, modified station access for the public and residents of The Residences Water Square and Riverfront Apartments and Condominiums. Selected areas must close to protect passengers and pedestrians from active hazards during extensive interior and exterior repairs.
The City of Detroit is a partner in improving access to the Water Square neighborhood. Its published community-benefits commitments include:
The City also committed to authorizing DTC to use up to $500,000 in unspent capital funds for station improvements through December 31, 2026. These are published commitments; individual work schedules and completion status are provided by the City.
Construction began September 14, 2026. The plan keeps the station open with modified access for the public and neighboring residents. Elevator availability and access routes can change during construction. Check current People Mover service notices before traveling.
The arrangements below describe the construction plan. Current service notices take precedence.
The plan calls for fencing barricades and temporary ramp closures to protect passengers and pedestrians while work takes place.
Planned street access uses the station elevator between Street Level and Platform Level, when in service, and the North Exit Stairwell. Consult current service notices for elevator outages and available accessible routes.
The plan reserves Level 2 access for Riverfront Apartments and Condominiums tenants. It directs tenants from the pedestrian crosswalk to the stairwell directly across, leading upward to Platform Level.
The platform elevator travels to and from the street and does not stop on Level 2. Accessible boarding is through the street-level elevator when it is in service.
At the August 27, 2026 Board meeting, DTC reported that the construction plan was in place with a planned end date of March 6, 2027. The station update continues to describe completion in early March 2027.